Billing Rates
Facilities Operations and Development has the desire and technical expertise to perform your department services that are not covered by POM funding. Some of these projects may require submitting a Project Request.
Examples of Billable Services
- Minor renovations, conversion of space, installation and/or maintenance of specialized equipment affecting the building systems.
- Repair of department equipment, such as window air conditioners, furniture, etc.
- Installation of items that require only minor modifications, such as pictures, wall brackets, wall clocks, etc.
- Fabrication of shelves and equipment, non-scheduled painting, changing ventilation equipment, adding electrical service, etc.
Billing Rates
Campus Services
Year | FY2015 | FY2016 | FY2019 | FY2020 |
Skilled Crafts Regular |
$40.25/hr |
$40.25/hr |
$40.25/hr |
$46.00/hr |
Campus Service Regular |
$38.10/hr |
$38.10/hr |
$38.10/hr |
$43.50/hr |
Custodial Regular |
$28.00/hr |
$28.00/hr |
$28.00/hr |
$32.00/hr |
Consultant Regular |
$41.10/hr |
$41.10/hr |
$41.10/hr |
$47.00/hr |
Solid Waste Truck (hourly) | $112.00/hr | $112.00/hr | $112.00/hr | $112.00/hr |
Solid Waste Pick-up | $29/stop | $29/stop | $30/stop | $31/stop |
Vac Truck or Crane Truck | $75/hr | $75/hr | $75/hr | $75/hr |
Trucks and Large Equipment | $30/hr | $30/hr | $30/hr | $30/hr |
Landscape Truck | $30/hr | $30/hr | ||
Bucket Truck | $52/hr | $52/hr | ||
Street Sweeper | $52/hr | $52/hr | ||
Moving Services can be arranged when in conjunction with capital projects. | Call S2F for a quote. | Call S2F for a quote. | ||
Trash Disposal - Customer must dump trash at the compaction center (2566 Kenny Road). | $31.55/cu.yd. | $31.55/cu.yd. | $31.55/cu.yd. | $31.55/cu.yd. |
Dumpster - Billed at our cost. Includes delivery & pick-up. | $82.50/unit | $82.50/unit | $82.50/unit | $82.50/unit |
Mower | $30/hr | $30/hr |
* Rates do not include delivery & set-up (billed at Campus Services rates above).
Design and Construction
Year | FY2015 | FY2016 | FY2019 | FY2020 |
<$1M* | 5.00% | 5.00% | 2.00% | 2.00% |
$1M - $4M* | 2.50% | 2.50% | 2.00% | 2.00% |
$4M - $20M* | 2.25% | 2.25% | 2.00% | 2.00% |
20M+* (b) | 2.00% | 2.00% | 2.00% | 1.50% |
Cost Estimating* | $500 | $500 | 2.00% | 2.00% |
State Project Fee** (a) | 1.50% | 1.50% | 1.50% | 1.50% |
* Total Project Cost
** Construction Budget
(a) State law limits the fee for local administration services for any project that includes state funds to 1.5% of the total construction cost.
(b) For projects funded on or after 7/1/18, tiered fee (first $20M of project is at 2%); anything above $20M is at 1.5%.
Special Events
Year | FY2015 | FY2016 | FY2019 | FY2020 |
Trash Drums - 55 gallons | TBD | TBD | ||
Trash Drums* - 55 gallons | 1 hr min set-up | 1 hr min set-up | ||
Trash Drums* - 55 gallons | 2 hr min set-up | 2 hr min set-up | ||
Trash Drum Liners | $0.50 ea | $0.25 ea | $0.25 ea | $0.25 ea |
Biodegradeable Liners | $1.00 ea | $1.00 ea | $0.70 ea | $0.70 ea |
Large Biodegradeable Liners | $2.00 ea | $2.00 ea | $2.00 ea | $2.00 ea |
Zero Waste Trash Can | $3.75 ea | $3.75 ea | $3.75 ea | $3.75 ea |
Information Planning and Design
Year | FY2015 | FY2016 | FY2019 | FY2020 |
Building Drawing Archives - 1-hour Min | $41.10/hr | $41.10/hr | $41.10/hr | $41.10/hr |
Campus Mapping - 1-hour Min | $41.10/hr | $41.10/hr | $41.10/hr | $41.10/hr |
Utility Marking Regular |
$41.10/hr |
$41.10/hr |
$41.10/hr |
$41.10/hr |
Radiation Safety
Year | FY2015 | FY2016 | FY2019 | FY2020 |
Damanged, lost, late badge (dosimeter) | $15.00 ea | $15.30 ea | $19.10 ea | $19.48 ea |
Genesis Ultra 36 MCP TLD badge | $1.84/mo | $1.88/mo | $2.05/mo $6.15/qtr | $2.10/mo $6.27/qtr |
Ultra or flex ring 18 badge | $2.86/mo | $2.92/mo | $3.18/mo $9.55/qtr | $3.25/mo $9.75qtr |
35 MCP TLD + Cr39 Badge | $9.18/mo | $9.36/mo | $9.93/mo $13.24/qtr | $10.13/mo $13.50/qtr |
Badge Board Small |
$25.50 |
$26.01 |
$27.60 ea |
$28.15 ea |
Radioactive Waste Removal
Year | FY2015 | FY2016 | FY2019 | FY2020 |
Dry Active Waste (offsite disposal) | $292.75/cu.ft. | $298.60/cu.ft. | $316.78/cu.ft. | $323.20/cu.ft. |
Dry Active Waste (decay) | $127.50/cu.ft. | $130.05/cu.ft. | $138.00/cu.ft. | $140.76/cu.ft. |
Mixed Waste | Actual Cost | Actual Cost | Actual Cost + Labor | Actual Cost + Labor |
Sealed Sources | Actual Cost | Actual Cost | Actual Cost + Labor | Actual Cost + Labor |
Environmental Reporting (private corp. rate) | $55.80/hr | |||
Permit Fees (private corp. rate) | Cost + 15% | |||
Lu-177 Patient Waste Dispotal | $208/patient treatment | |||
Radiation Meter Repair | Actual Cost + Labor | |||
Disposal and Repair Rate | $41.92/hr | $42.75/hr |
Utilities
2020 - when available, will be posted at Business and Finance website > Planning Assumptions section > Direct Billed Utility Rates